Project extension
- If a no-cost extension of time is needed to complete the project, the head researcher must submit a preliminary extension request to the unit 6o days before the project end date using the appropriate form approved by the general secretariat, including:
- A financial report showing the outstanding balance of the project budget.
- A technical plan for the extension period.
- A detailed and scheduled budget for the extension period, excluding the research team or project manager’s remuneration.
- A budget increased cannot be requested for the extension period.
- The general secretariat is notified of the unit’s decision with justification.
- The extension period is subject to the same technical and financial regulations governing the project performance during the original estimated time, provided it does not include any:
- Remuneration for the researchers or the project manager.
- Changes in the project goals.
- Budget increase.
- The project duration cannot be extended more than once.